Transit track construction
City of Calgary Transit LRT Track Work
Ironhorse crews and equipment on City of Calgary LRT track: the Haysboro Storage Facility expansion, a crossover replacement and station track work.

The operating challenge
Calgary's LRT runs through the work. The Haysboro Storage Facility had to stay in operation while it was extended for four-car trains, and crossover and station work had to fit closures on live transit track beside traffic and the public.
Published project details
Track work inside the expanded Haysboro Storage Facility
LRT crossover replacement, with track panels set by crane
Track work at an LRT station platform
Loaders, track machines and crews working within transit closures
The delivery outcome
The City reports that the Haysboro expansion, built from January 2024 to January 2026 to store four-car trains, is now in operation. Ironhorse's photographs show its crews and equipment inside the facility, on the crossover replacement and at station track.
Published details are taken from the linked independent record.